How long does a NYC townhouse renovation take?
NYC Townhouse Renovation Design Study
A townhouse renovation in New York City typically takes between 8 and 24 months from the start of design to the completion of construction. The timeline depends on the scope of the renovation, the condition of the existing building, and the complexity of the design.
We like to think of the process in four phases. These phases are programming, design, permitting, and construction. Each stage plays an important role in shaping the project and preparing it for the next.
For homeowners unfamiliar with the construction process, engaging an architect early can be extremely valuable. An architect can guide the project through all four stages while helping avoid costly mistakes and maintain an overall design thesis that is tailored to the owner's lifestyle.
Massing diagram exploring the possibility of adding additional floors to an existing Brooklyn townhouse
Programming
Programming, sometimes called pre-design or pre-construction planning, is the phase where the architect and owner begin to understand the existing building and the goals of the project. This stage often includes walkthroughs of the property, professional surveys, zoning reviews, and early sketches that test different possibilities for the building.
These early studies can answer questions such as how many units might fit in a building, whether an additional floor may be possible, or how the existing structure might be reorganized to better suit the owner’s needs.
For one project, we assisted a developer in understanding how many units could fit inside an existing multifamily building and the difficulty involved in adding two additional floors. The resulting diagrams made by our team showed the owner the true cost of the investment that would be required for the project to generate a positive cash flow. With that information the owner chose to pause the project and begin saving so that the renovation could be started later with stronger financial footing. In this way the programming phase helped the owner avoid entering construction without the resources needed to complete the project successfully.
One of the unique aspects of renovating buildings in New York City is that properties often come with a list of prior violations or issues from previous ownership. Before construction can begin, the building must often be brought back into compliance with the building code.
Many of these issues can be discovered early by reviewing public records. Owners can start by reviewing zoning and lot information through the New York City Zoning and Land Use Application database, commonly known as ZOLA. From there it is possible to navigate to the Building Information Number, which contains records of violations, permits, and other historical information about the building.
This early research helps owners understand whether a property is worth the investment required to renovate it. Violations can also provide insight into possible structural, plumbing, or safety issues that may need to be addressed before focusing on the design of the renovation itself.
Programming can be thought of as a discovery phase. During this time the architect works with the owner to understand the constraints of the project such as budget, timeline, structural limitations, and zoning restrictions. At the same time the architect also tries to understand the ambitions of the owner and the type of life they hope the space will support.
Interior Design Rendering Study for NYC Townhouse Renovation
Design
Design is often misunderstood as simply choosing finishes or cabinetry. Architects view design much more holistically. The structure of the building influences how rooms can be organized. The location of plumbing stacks affects where bathrooms can be placed. Window placement influences which spaces should become bedrooms, offices, or living areas.
There are many variables that must work together. The architect’s role is to prioritize these variables and create relationships between them so that the building functions well and reflects the lifestyle of the owner.
The design phase is also closely tied to financial planning. The drawings produced by the architect describe the materials, quantities, and specifications that will ultimately be built. The more accurate the drawings are, the more accurate the contractor’s estimates will be. Accurate drawings also allow contractors to produce more reliable construction schedules.
For smaller renovations the design phase may take around three months. For a full townhouse renovation it is common for the design phase to last six months or longer. Spending more time planning often reduces the number of surprises that occur once construction begins. In many cases the goal is to spend more time designing so that less time and money are spent resolving problems during construction.
On a recent project in Gowanus, Brooklyn we completed a full gut renovation of a townhouse that had been abandoned by the previous owner. Our clients were local homeowners whose children had recently gone off to college and they wanted to downsize into a smaller townhouse while creating a rental unit on the first floor.
The project required roughly eight months of design work. During the design phase we produced drawings, renderings, and virtual walkthroughs so the owners could clearly understand how the finished home would feel. We typically meet with clients every two weeks during this stage so that the design evolves through an ongoing conversation between the architect and the owner.
Once the design is complete and the owner feels comfortable moving forward, the project enters the permitting phase.
Section drawing illustrating the interior organization of a Brooklyn townhouse renovation including residential spaces and rooftop studio
Permitting
The permitting phase involves obtaining approvals from the New York City Department of Buildings before construction can begin. During this stage the architect prepares the drawings and supporting documents required for submission.
Permits are typically filed through the Department of Buildings online portal known as DOB NOW. The submission usually includes architectural drawings, an asbestos inspection report, and a legal survey prepared by a licensed surveyor. If the sidewalk or street trees are affected by the project, additional documentation may also be required.
During this phase the owner also selects a general contractor for the project. A common strategy is to invite at least three contractors to review the drawings and submit proposals. The architect can then compare the proposals to confirm that each contractor has accounted for the full scope of work.
While the lowest bid may appear attractive, the goal is usually to select the lowest responsible bid. This means choosing a contractor who has accurately priced the project and understands the complexity of the work.
Approval timelines can vary depending on the borough and the complexity of the project. In many cases approvals may take between three and eight weeks. The plan examiner reviewing the drawings is primarily focused on ensuring that the project complies with building code requirements and does not endanger the health and safety of occupants or the public.
We are currently waiting on approvals for the renovation of an existing apartment within a Brooklyn townhouse that will be transformed into an artist studio capable of showcasing artwork along with a one bedroom residence.
When reviewing renovations of existing buildings, plan examiner comments often focus on light and air compliance to ensure that habitable spaces meet the requirements of the building code. This can influence the placement of bedrooms, living spaces, and windows.
The goal of the architect during this stage is to respond to these comments in a way that satisfies the requirements of the New York City Department of Buildings while still preserving the design intention of the project and the goals of the owner.
Once approvals are issued, the contractor can pull the permits and construction can begin.
Wood framing installation during the construction phase of renovation
Construction
During construction the contractor builds the project based on the approved drawings. Renovations in New York City often reveal unexpected conditions once demolition begins. Older buildings sometimes contain hidden structural issues or outdated systems that were not visible during the design phase.
When these situations arise the architect works with the contractor to develop solutions that respect the overall design and keep the project moving forward.
There are also several ways owners can help the construction process run more smoothly. Informing neighbors about upcoming construction can reduce conflicts. Access agreements may need to be coordinated with adjacent properties. Utility upgrades such as electrical service improvements or sewer connections may also require early coordination.
Another helpful step is ordering appliances and other large equipment early in the process. Many items have long lead times and purchasing them in advance can prevent delays later in construction.
During construction the architect will flag these items and materials and check in with the contractor to ensure that the work is progressing properly and remains aligned with the drawings.
Throughout construction the architect continues to support the project by answering contractor questions, reviewing submittals, and helping resolve issues that appear on site.
Final Thoughts
A townhouse renovation in New York City is a complex process involving many moving parts. Reach out to our email at info@copa.nyc and we can schedule a free one hour consultation about your project. We can discuss your goals, review the property, and explore the services we offer that may help guide the project forward.